Uzbekistan · Tashkent Reference Config

Metal Sandwich Panel Roofing · Tashkent

Textile factory expansion with 2,500m² insulated metal roofing. JYYJ-Q300 pneumatic delivered high-output application at entry-level cost structure.

Metal Sandwich Panel Roofing · Tashkent

Customer Type

Textile Manufacturing

Industry

Textile Manufacturing

Project Scale

2,500 m²

Duration

6 days

The Challenge

New textile production hall needed insulated metal sandwich roof panels. Customer budget favored pneumatic equipment; 2,500m² scale required 2-12 kg/min throughput for timely completion.

Our Solution

JYYJ-Q300 pneumatic at 25 MPa provided 2-12 kg/min output for 2,500m² on schedule. Applied 50mm open-cell PU foam at 12 kg/m³ between steel panel skins. Pioneer All-Water A-component (zero-ODP) met local environmental preferences.

What Pioneer Delivered

Not just a machine — a matched system, a trained crew on site, and after-sales backing end to end.

  • An on-site review of the panel line and 2,500m² roof schedule, sizing the cavity gap and daily output so the textile hall finished on time.
  • A single-source system — the JYYJ-Q300 machine and matched Pioneer foam tuned and warranted together, not a budget machine and mystery chemicals from three suppliers blaming each other.
  • A spray crew trained to hold 12 kg/m³ core density to ±1 kg/m³ across a high-output pneumatic run — the hard part of panel foam is the operator, and we own it.
  • QA on cavity fill and a spray schedule built around the factory expansion window — 2,500m² of insulated roofing completed in 6 days, not weeks.
  • Ongoing remote support for output and ratio tuning, plus easy re-order of the exact matched All-Water foam — so the next panel run is a phone call, not a new sourcing project.

Execution Process

  1. 1 · Panel Cavity Prep

    Steel panel skins are degreased and dried, then the cavity gap is set with spacers for a uniform 50mm core thickness. Skin temperature is checked so the open-cell foam rises and bonds evenly between the sheets.

  2. 2 · Pneumatic Machine Setup

    The JYYJ-Q300 pneumatic unit is primed with Pioneer All-Water A-component and matched B-component, output set within the 2-12 kg/min band at 25 MPa. A short test shot confirms density before production spraying begins.

  3. 3 · Open-Cell Core Spray

    50mm open-cell PU foam at 12 kg/m³ is sprayed between the steel skins, the stable pneumatic output holding density to ±1 kg/m³ across the 2,500m² roof. A 2-person crew sustains roughly 420 m² of finished panel per day.

  4. 4 · Trim, Cure & Closure

    Excess rise at panel edges is trimmed flush, then the core cures and the panels are closed and fixed to the roof structure. Each completed panel is checked for full cavity fill before installation on the production hall.

Key Technical Highlights

Foam Core

50mm open-cell PU @ 12 kg/m³

Lightweight open-cell core for cost-efficient panel insulation.

Spray Unit

JYYJ-Q300 @ 25 MPa

Pneumatic plural-component rig with 2-12 kg/min stable output.

A-Component

Pioneer All-Water (zero-ODP)

Water-blown chemistry meeting local environmental preferences.

Daily Output

420 m²/day

Sustained by a 2-person crew across the 2,500m² roof.

Density Consistency

±1 kg/m³

Stable pneumatic output holds even core density panel to panel.

Equipment Investment

$3,250

Entry-level cost versus $30k+ for the Western equivalent.

Project Gallery

On-site application and finished surfaces from this project.

Metal Sandwich Panel Roofing · Tashkent — on-site view 1

Reference Design Targets

Design and specification targets for this application — not measured results from a specific customer project.

420 m²/day

Panel output

2-person crew

±1 kg/m³

Foam density consistency

pneumatic stable output

$3,250

Equipment investment

vs $30k+ Western equivalent

R-3.5 per inch

R-value

open-cell configuration

Why This Model Is Commonly Selected

The JYYJ-Q300 is an air-driven mid-range machine (30 MPa, 2–10 kg/min) commonly selected for residential and light-commercial insulation — lower initial investment and straightforward maintenance (an air compressor is required).

Frequently Asked Questions

What size compressor does the Q300 need?
Pneumatic machines typically need around 980 L/min at 8 bar or above; the compressor is sold separately.
Can the Q300 spray closed-cell foam?
Yes — it sprays polyurethane foam; the exact material and density depend on your insulation goal and supplier formulation.

Recommended Configuration

  • Main proportioning unit
  • Fusion-compatible spray gun
  • Two transfer pumps
  • 15 m heated hose (7 m on D casting models)
  • Tool kit
  • IPPC export wooden case

Spray Foam Material Estimator

Estimate polyurethane foam material for your project. Enter area, thickness, density and waste allowance.

Foam Volume
Foam Weight
Material (A + B)
Est. Spray Time

Estimated values only. Actual consumption varies with substrate condition, operator technique, overspray and material performance. Assumes ~1:1 A/B and ~8 kg/min output.

For Industrial Buyers · Skip the Form

Planning a similar project?

Share your output, voltage, and project scale. Pioneer recommends a matched JYYJ machine + material combination within 24 hours.

✓ ISO 9001 certified plant in China ✓ Reply within 24 hours ✓ TDS · MSDS · COA on request ✓ Mon–Fri 9–18 (UTC+8)

Reference Configuration: This page shows a reference machine configuration for a typical application, based on Pioneer's equipment specifications — not verified performance data from a specific customer project. Figures are design targets or typical values, not measured results. Verified delivery records (real machine + destination country + shipment photos) and documented customer projects are available on request.

Get a Quote