Industrial Facility Flooring Coating · Riyadh
Manufacturing facility 6,000m² floor with polyurea topcoat. Abrasion + chemical resistant high-gloss finish. Production downtime limited to weekend.
Customer Type
Industrial Manufacturing Facility
Industry
Industrial Manufacturing
Project Scale
6,000 m²
Duration
52 hours (weekend)
The Challenge
Active manufacturing plant could only suspend operations 48-60 hours. Existing floor failing under forklift traffic + chemical spills. Required abrasion + chemical resistance with near-zero cure to meet Monday production restart.
Our Solution
Weekend application window. JYYJ-H-V6T at 36 MPa with 2-14 kg/min throughput completed full coverage in 38 hours. Polyurea flooring grade 3mm DFT, primed to concrete. Full cure to forklift traffic in 6 hours post-application.
What Pioneer Delivered
Not just a machine — a matched system, a trained crew on site, and after-sales backing end to end.
- An on-site slab survey with moisture and dew-point logging before any spray, plus crack and joint routing — so the coating bonded to a sound floor instead of lifting under traffic.
- A single-source system — JYYJ-H-V6T machine and flooring-grade polyurea matched, tuned and warranted together, not a sprayer, a primer and a coating from three suppliers blaming each other.
- A spray crew trained for large-area floor work and high-throughput application — the hard part of a seamless 6,000 m² floor is operator pace and overlap control, and we own it.
- Holiday-tested QA and a schedule built around the plant's 48-60 hour weekend shutdown — the full floor went back to forklift traffic in 6 hours and production restarted on time Monday.
- Ongoing remote support for ratio and temperature tuning, plus re-order of the exact matched material — so the next bay or a worn zone is a phone call, not a new project.
Execution Process
-
1 · Concrete Prep & Shot Blast
The 6,000 m² slab is shot-blasted to a CSP 3-4 profile to strip old coating, laitance and oil, then cracks and joints are routed and filled so the polyurea lays over a sound, keyed substrate.
-
2 · Primer & Moisture Check
Slab moisture and the weekend dew point are logged, then a concrete-matched epoxy primer is rolled within the recoat window for chemical adhesion across the full floor before the topcoat goes down.
-
3 · Polyurea Floor Spray
Flooring-grade pure polyurea is sprayed to 3 mm DFT with the JYYJ-H-V6T at 36 MPa, sustaining 2-14 kg/min and roughly 6 m²/minute to cover the whole plant inside the weekend window. A seamless high-gloss film leaves no joints for forklift wheels to chip.
-
4 · Cure & Monday Restart
The polyurea is tack-free within minutes and reaches full forklift-traffic cure in 6 hours, leaving margin inside the 48-60 hour shutdown. The floor is holiday-checked for pinholes, then production restarts on schedule Monday morning.
Key Technical Highlights
Coating System
3 mm flooring polyurea
Flooring-grade pure polyurea, seamless high-gloss finish over concrete.
Spray Unit
JYYJ-H-V6T @ 36 MPa
Heated plural-component rig sustaining 2-14 kg/min for large-area work.
Throughput
~6 m²/minute
Sustained spray rate covered 6,000 m² in 38 application hours.
Surface Prep
CSP 3-4 + epoxy primer
Shot-blast profile plus concrete-matched primer for chemical bond.
Abrasion Resistance
Taber H-18
Under 80 mg loss per 1000 cycles, holds up to forklift traffic.
Return to Service
6 hours to forklift
Full cure inside the 48-60 hour window for an on-time Monday restart.
Project Gallery
On-site application and finished surfaces from this project.
Reference Design Targets
Design and specification targets for this application — not measured results from a specific customer project.
38 hours
Total application time
6 m²/minute sustained
On schedule
Production restart
Monday morning
Taber H-18
Abrasion resistance
<80mg loss/1000 cycles
Full spectrum
Chemical resistance
acids, solvents, alkalis
Why This Model Is Commonly Selected
The JYYJ-H-V6T adds a 7-inch PLC touchscreen to the hydraulic V6 platform for precise temperature and pressure control — useful for tank lining, industrial flooring and abrasion-resistant coatings where consistent film thickness matters.
Frequently Asked Questions
Difference between H-V6 and H-V6T?
Good for pure polyurea lining?
Recommended Configuration
- Main proportioning unit
- Fusion-compatible spray gun
- Two transfer pumps
- 15 m heated hose (7 m on D casting models)
- Tool kit
- IPPC export wooden case
Spray Foam Material Estimator
Estimate polyurethane foam material for your project. Enter area, thickness, density and waste allowance.
Estimated values only. Actual consumption varies with substrate condition, operator technique, overspray and material performance. Assumes ~1:1 A/B and ~8 kg/min output.
Planning a similar project?
Share your output, voltage, and project scale. Pioneer recommends a matched JYYJ machine + material combination within 24 hours.
Reference Configuration: This page shows a reference machine configuration for a typical application, based on Pioneer's equipment specifications — not verified performance data from a specific customer project. Figures are design targets or typical values, not measured results. Verified delivery records (real machine + destination country + shipment photos) and documented customer projects are available on request.